  • The demolition of building number 5, next to the railway line, was completed.
  • Half of building number 7, also next to the railway line and the last remaining structure, was demolished.
  • Eleven containers of demolition debris were transported to the subsurface solid waste containment site operated by the RIGMRBM near Cowansville.
  • Ten containers of metal waste were sent for recycling.
  •  Artifacts relating to the former Filtex factory were saved and relocated by Town employees.
  • For questions or comments concerning the Filtex demolition please contact the Public Works Secretary, Jessica Savard, by phone at 450 538-2290 or by email to [email protected]