Filtex : weekly update – October 7 to 11, 2019

Published on October 11, 2019
  • Concrete crushing at the Mont-Écho municipal site ended Wednesday, October 9th;

  • In total, the concrete removed from the Filtex site took 5 days to crush for future re-use;

  • The Phase II Environmental Site Assessment took place Wednesday and Thursday, October 9th & 10th;

  • Topsoil will be laid down on Tuesday and Wednesday of next week, October 15th & 16th.

  • For questions or comments concerning the Filtex demolition please contact the Public Works Secretary, Jessica Savard, by phone at 450 538-2290 or by email to [email protected]

 

 