Filtex : weekly update – September 3 to 6, 2019

Published on September 6, 2019
  • The demolition of building 7 next to the railway line, was completed.
  • All Filtex structures have now been demolished.
  • No damage was incurred to the infrastructure surrounding the demolition site. Congratulations to the operators of the 2 mechanical excavator.
  • Four containers of demolition debris were transported to the subsurface solid waste containment site operated by the RIGMRBM near Cowansville.
  • 5 containeers of metal waste were sent for recycling.
  • All artifacts relating to the former Filtex factory have now been recovered.
  • The security fence now surrounds the entire perimeter of the demolition site.
  • A representative of the CMQR railway company has been present at the demolition site to ensure railway safety.
 