Notice of work on Vallée-Missisquoi road from July 8 to July 11, 2019

Town of Sutton wishes to inform citizens that the Ministère des Transports will be reconstructing a culvert at the intersection of Vallée-Missisquoi road and Scenic road.

Hindrance:

Complete closure from Monday, July 8th at midnight to Thursday, July 11th at 6:59 am. Alternating circulation on Thursday, July 11th between 7 am to 5 pm.

Start:

Monday, July 8th at midnight

Finish:

Thursday, July 11th at 5 pm

Location:

At the intersection of Vallée-Missisquoi road and Scenic road

Detour:

Scenic Road, R-139, R-215, R-243 and Vallée-Missisquoi Road (approximately 80 km)

Identification of work:

Reconstruction of a culvert

These interferences may be altered due to operational or weather constraints. Consult Québec 511 to follow-up the work.