Public information session on the upcoming Western Street construction site

Reconstruction work on the northern section of Western Street (between Principale Street North and Route 215) will begin on April 29 and last until October 18, 2024. Given the size of the project and its temporary impact on local residents as well as on users of the Goyette-Hill Park, the Town of Sutton invites you to a public meeting on Tuesday, March 26, from 6:30 to 8:30 p.m., to obtain all the information you need and answer any questions you may have.

An initial public presentation of the planned investment took place on May 9, 2023. We are currently in the start-up phase. The Public Works and Fixed Assets Department, accompanied by the engineer from FNX Innov inc. who is in charge of the project, will present a concrete overview of all the stages of the upcoming worksite and the nature of the work: replacement of underground infrastructures (aqueduct, sanitary sewer and storm sewer), redevelopment of the street (pavement, sidewalks and concrete curb) and of the two parking lots in Parc Goyette-Hill.

The presentation will be recorded and broadcast on the Town’s YouTube channel.

Information booths at the public meeting

Following the presentation, Western Street residents and users of Goyette-Hill Park facilities will be able to ask questions at the two information booths set up for this purpose:

Public Works and Fixed Assets Department information booth: to answer questions from concerned residents, such as the collection of residual materials during this period, access to their homes, traffic, planned means of communication, CITAM registration, etc.

Recreation, Community Life and Culture Department information booth: to answer questions about the use of Goyette-Hill Park during this period, such as access to the park, alternative parking, day camp, aquatic and other activities planned on the grounds, etc.

RECONSTRUCTION WORK ON WESTERN STREET (NORTH)
Dates: April 29 to October 18, 2024
Investment: $6,900,000
Contractor: Excavation St-Pierre & Tremblay inc.
Engineering firm responsible for work supervision and materials control: FNX Innov inc.