Western Street reconstruction site – Work Info as of May 24, 2024

The Public Works and Fixed Assets Department wishes to provide you with this important update for the upcoming week of May 27th.

In the southern parking lot of Goyette Hill Park: the parking lot will still be closed all week.

In the northing parking lot of Goyette Hill Park: the parking lot will still be closed all week.

Park users will be able to enter the park via the bicycle path. The use of alternative parking is mandatory.

Start Phase 1: for Western Street (North), between Principale Nord Street and building number 93.

Period: from May 27 to June 14 (3 weeks)

Restrictions: complete closure of Western Street at the intersection of Principale Nord Street.

  • Detours via Pleasant Street (Road 215), Academy Street and Principale Nord Street.

Work may be modified or cancelled due to operational constraints or weather conditions.

FOR ANY QUESTION ON THE WORKSITE
Contact the Public Works and Fixed Assets Department :
by telephone at 450 915-6684
by e-mail at [email protected]
Ongoing Information on sutton.ca/western2024